首页   按字顺浏览 期刊浏览 卷期浏览 The Slurry Trench Cut-off for the Duncan Dam
The Slurry Trench Cut-off for the Duncan Dam

 

作者: D. R. Duguid,   D. J. Forbes,   J. L. Gordon,   O. K. Simmons,  

 

期刊: Canadian Geotechnical Journal  (NRC Available online 1971)
卷期: Volume 8, issue 1  

页码: 94-108

 

ISSN:0008-3674

 

年代: 1971

 

DOI:10.1139/t71-008

 

出版商: NRC Research Press

 

数据来源: NRC

 

摘要:

A slurry trench cut-off was constructed for the Duncan Dam. Two failures of the trench wall occurred during construction, one of which required relocation of a portion of the cut-off to avoid delaying construction of the dam. The relocated cut-off was successfully constructed from a higher ground elevation, using a denser slurry, produced by mixing in more silt. To analyze the failures a nomograph was developed which can be used to determine the required slurry density for trench wall stability. The stability analysis, first developed by Morgenstern and Amir-Tahmasseb was confirmed. The hydrostatic head drop across the cut-off varies from 85 to 90 % of the gross head on the dam. Differential settlement of almost 10 ft (3 m) has occurred along the cut-off after completion without detrimental effects. Readings over the last 3 years indicate no reduction in the efficiency of the cut-off.

 

点击下载:  PDF (2526KB)



返 回